Pool Updates

Throughout the quarantine, Aqua, Stewart Excavating, and Marth Masonry have been busy! 

 

While the past month has not been kind to us from a weather standpoint, we are now once again making good progress on the pool renovation project. After weeks of monsoon-like weather we have taken advantage of recent dry spell. Concrete prep work began on Monday 5/18 and we were able to pour the first loads of concrete today (5/21). After some more prep work Friday we will begin pouring the remaining deck areas and the new splash pad on Tuesday 5/26. Concrete work should finish up by Friday the 29th weather permitting. Final pool finish is scheduled to be applied on June 8th and we will begin filling the pool the following day. While I am disappointed we did not make our target date we are still waiting to hear from Governor Hogan about when and under what conditions we will be allowed to open the pool. With a little luck we will be ready to go when we get the go ahead to open!